Project Summary

Wastewater Management
SEWERAGE AND WASTEWATER TREATMENT PLANT (WWTP) DESIGN FOR MUNICIPAL DISTRICT OF AGIOS LOUKAS OF MUNICIPALITY OF KRYA VRYSI, PELLA PREFECTURE

Client: Municipal Water Wastewater Utility of Kria Vrisi
Year: 2008
Budget: 6.746.650€

ISSUE
The purpose of the project was:

SOLUTION
The collected wastewater was discharged untreated in the broader region, resulting in the degradation of the natural environment and the quality of life for local residents.

The table below shows the total peak population of all communities, for each design phase.

Peak Population of Served Communities
Community Population 2001 Projected Population in 2008 Projected Population in 20 years Projected Population in 40 years
Agios Loukas 1.555 1.780 2.619 3.854
Akrolimni 1.340 1.534 2.257 3.321
Esovalta 989 1.132 1.666 2.451
Stavrodromi 556 636 937 1.378
Total 4.440 5.083 7.479 11.00

The design of the project was pursuant to the Greek Presidential Decree 696/74. The design of the pipelines, the pumping stations and the WWTP, was based on a 40-year horizon, while the selection of the electrical and mechanical equipment was based on a 20-year horizon. Specifically, the project included:

BENEFIT
The sewerage and WWTP design solved the wastewater problem for communities of Agios Loukas, Akrolimni, Esovalta and Stavrodromi of Municipality of Kria Vrisi.