Project Summary

Wastewater Management
WASTEWATER COLLECTION AND TREATMENT DESIGN FOR THE MUNICIPALITY OF KERAMOTI, KAVALA PREFECTURE

Client: Municipality of Keramoti
Year: 2008
Budget: 7.450.000 €

ISSUE
The purpose of the project was the Δήμος  Κεραμωτήςpreliminary design of the:

SOLUTION
The aforementioned communities were served by septic tanks. The produced wastewater was discharged untreated in the broader region resulting in the degradation of the natural environment and the quality of life for local residents.

The table below shows the total peak population of all communities, for each design phase.

Peak Population of Served Communities
COMMUNITY
POPULATION (2001)
WINTER POPULATION
SUMMER POPULATION
8-YEAR POPULATION (2009)20-YEAR POPULATION (2029)40- YEAR POPULATION (2049)
PEAK POPULATION (2009)20-YEAR POPULATION (2029)YEAR POPULATION (2049)
Keramoti 1.228 1.364 1.773 2.455 2.678 3.482 4.820
Chaidefto 475 475 618 855 475 618 855
TOTAL 1.703 1.839 2.391 3.310 3.153 4.100 5.675

The design of the project was pursuant to the Greek Presidential Decree 696/74. The design of the pipelines, the pumping stations and the WWTP, was based on a 40-year horizon, while the selection of the electrical and mechanical equipment was based on a 20-year horizon. Specifically, the project included:

In summary, the WWTP consists of the following units: 

BENEFIT
The design of the sewer pipelines and the WWTP solved the wastewater problem for the communities of
Keramoti and Chaidefto of the Municipality of Keramoti.