Project Summary

Wastewater Management
WASTEWATER AND STORMWATER FINAL DESIGN UPDATE FOR COMMUNITIES LITI AND MELISOCHORI OF MUNICIPALITY OF MIGDONIA, THESSALONIKI PREFECTURE

Client: Municipal Water Wastewater Utility of Migdonia
Time: 2008
Budget: 7.005.000€

ISSUE
The purpose of the project was the ΕΠΙΚΑΙΡΟΠΟΙΗΣΗ ΟΡΙΣΤΙΚΗΣ ΜΕΛΕΤΗΣ ΔΙΚΤΥΩΝ ΑΠΟΧΕΤΕΥΣΗΣ ΚΑΙ ΑΓΩΓΩΝ ΜΕΤΑΦΟΡΑΣ ΑΚΑΘΑΡΤΩΝ ΥΔΑΤΩΝ Δ.Δ. ΛΗΤΗΣ ΚΑΙ ΜΕΛΙΣΣΟΧΩΡΙΟΥ ΔΗΜΟΥ ΜΥΓΔΟΝΙΑΣfinal design update for the construction of:

SOLUTION
The aforementioned communities were served by septic tanks. The produced wastewater was discharged untreated in the broader region resulting in the degradation of the natural environment and the quality of life for local residents.
 
The table below shows the total peak population of all communities, for each design phase. 

Peak Population of Served Communities
Community Population 2008 Projected Population in 20 yearsProjected Population in 40 years
Liti 6.800 7.120 7.600
Melisochori 4.052 4.239 4.520
TOTAL 10.852 11.359 12.120

The design of the project was pursuant to the Greek Presidential Decree 696/74. The design of the pipelines and the pumping stations was based on a 40-year horizon, while the selection of the electrical and mechanical equipment was based on a 20-year horizon. Specifically, the project included:

BENEFIT
The design of the aforementioned project solved the sewer network problem for communities of Liti and Melisochori.