Client: Municipality of Iasmos
Year: 2002
Budget: 4.740.000€
The purpose of the project was the preliminary design of the sewer pipeline network for the municipal district of Iasmos as well as the external sewer networks and pumping stations for transporting the collected wastewater to the Waste Water Treatment Plant (WWTP) of Iasmos, which was proposed to be situated 2km south of Iasmos.
Peak Population of Served Communities | |||
Community | Population 2001 | Projected Population in 20 years | Projected Population in 40 years |
Iasmos | 3.000 | 3.661 | 4.467 |
TOTAL | 3.000 | 3.661 | 4.46 |
The design of the project was pursuant to the Greek Presidential Decree 696/74. The design of the pipelines, the pumping stations and the WWTP, was based on a 40-year horizon, while the selection of the electrical and mechanical equipment was based on a 20-year horizon. Specifically, the project included:
The wastewater design solved the wastewater problem for the community of Iasmos.