Project Summary

Solid Waste Management
RECEPTION BED FOR DRIED AND CALCIFICATED SLUDGE (50.000M³) FOR THE SANITARY LANDFILL SITE OF TAGARADES, THESSALONIKI
Client: Thessaloniki Water Supply and Sewerage CO.S.A
Time: 2008
Budget 510.000€

ISSUE
The purpose of the ΧΥΤΑ Ταγαράδωνproject was the final design of the bed for the deposition of produced sludge from the Waste Water Treatment Plant (WWTP) in “Galliko”, for safe temporary storage of the inert and calcificated sludge, until the construction of Sludge Thermal Treatment Plant.

SOLUTION
The produced sludge of the WWTP in “Galliko” – about 135tn/day – accumulates within the WWTP creating health problems (the sludge content is infectious) for workers on the site and residents of the broader region, as well as problems for the natural environment.

The proposed area for the construction of the bed is adjacent to the existing sanitary landfill of Tagarades, in a space within the boundaries of the landfill site.

The total capacity of the bed - taking into account the final grade work after the required earthworks, the slopes and the surface quality - is estimated at 50.000m³, while the lifetime of the bed is estimated to 372 days.

Concisely, the design of the project includes the following:
The collected quantity of leachate is transported by trucks to the existing WWTP.

BENEFIT
The design of the project solved the problem of temporary safe deposition of produced sludge from the WWTP in “Galliko”.